Services Unit Project Activity for WB 7/11/2016
Services Unit SL7 Server Upgrade - 358 -
Project358ServicesSL7Upgrade
Planned
: Neil - AIAI, finish afsdb0, beeknow
Actual
: Neil - afsdb0, ckankvm(edweb)
Next Week
: Neil - AIAI, huldra
Time Spent (hrs)
: Neil - 5.7
Investigate AFS on ECDF storage - 268 -
Project268AFSonECDF
Planned
: Nothing
Actual
: Nothing
Next Week
: Nothing
Time Spent (hrs)
: 0
Securing the Web - 287 -
Project287SecuringWebServers
Planned
: Nothing
Actual
: Nothing
Next Week
: Nothing
Time Spent (hrs)
: 0
School
EdWeb
- 364 -
Project364SchoolEdWeb
Planned
: Cosign web.inf
Actual
: Nothing
Next Week
: Cosign web.inf
Time Spent (hrs)
: 0
Deploy Git/Gerrit as full services - 272
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
Prometheus AFS Conduit
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
Research Data Audit
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
Archiving
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
CVS to SVN web - 226 -
Project226Status
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
Investigation and provision of meeting software - 333 -
Project333Status
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
Replacement Bug-tracking Tool
Planned
:
Actual
:
Next Week
:
Time Spent (hrs)
:
This topic: DICE
>
WebHome
>
ServicesUnit
>
ServicesUnitProjects
>
ServicesUnitProjectActivity20161107
Topic revision: r1 - 15 Nov 2016 - 17:20:26 -
NeilBrown
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki?
Send feedback
This Wiki uses
Cookies