Services Unit Project Activity for WB 26/9/2016

  • Services Unit SL7 Server Upgrade - 358 - Project358ServicesSL7Upgrade
    • Planned: Neil - keto. Look more at IPv6 networking. apacheconf headers.
    • Actual: Neil - keto and ladon done. Chat with roger about WP
    • Next Week: Neil - apache headers, AIAI web
    • Time Spent (hrs): Neil - 4.2

  • Investigate AFS on ECDF storage - 268 - Project268AFSonECDF
    • Planned: Nothing
    • Actual: Nothing
    • Next Week: Nothing
    • Time Spent (hrs): 0

  • School EdWeb - 364 - Project364SchoolEdWeb
    • Planned: Clone uoe_ease module, as inf_cosign.
    • Actual: Cloned uoe_ease module, as uoe_cosign. Didn't work frown Simple patch of uoe_ease does)
    • Next Week: Investigate why uoe_cosign didn't work.
    • Time Spent (hrs): 2.8

  • Deploy Git/Gerrit as full services - 272
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Prometheus AFS Conduit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Research Data Audit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Archiving
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • CVS to SVN web - 226 - Project226Status
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Investigation and provision of meeting software - 333 - Project333Status
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Replacement Bug-tracking Tool
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):
Topic revision: r1 - 30 Sep 2016 - 16:10:38 - NeilBrown
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback
This Wiki uses Cookies