Services Unit Project Activity for WB 14/09/2015

  • Investigate AFS on ECDF storage - 268 - Project268AFSonECDF
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • School EdWeb - 364 - Project364SchoolEdWeb
    • Planned: Finish dist update.
    • Actual: Hardly looked at the dist update. Did setup a bunch of redirects from old plone to new edweb pages. blogged
    • Next Week: Finish dist update.
    • Time Spent (hrs): 4.3

  • Deploy Git/Gerrit as full services - 272
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Prometheus AFS Conduit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Research Data Audit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Archiving
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • CVS to SVN web
    • Planned: Not much (Intro week, then Leave)
    • Actual: Nothing
    • Next Week: On Annual Leave
    • Time Spent (hrs): 0:00

  • Secure Web Server
    • Planned: Not much (Intro week, then Leave)
    • Actual: Nothing
    • Next Week: On Annual Leave
    • Time Spent (hrs): 0:00

  • Replacement Bug-tracking Tool
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):
Edit | Attach | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r2 - 18 Sep 2015 - 14:44:49 - NeilBrown
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback
This Wiki uses Cookies