- Investigate AFS on ECDF storage - 268 - Project268AFSonECDF
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):
- Deploy Git/Gerrit as full services - 272
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):
- Prometheus AFS Conduit
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):
- Research Data Audit
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):
- Archiving
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):
- CVS to SVN web - 226
- Planned: Further investigations into Institute publishing
- Actual: Further investigations into Institute publishing
- Next Week: Nothing (annual leave)
- Time Spent (hrs): 3:55
- Secure Web Server - 301
- Planned: Confirm sign-off documentation, etc.
- Actual: Apache/suexec RPM restructuring investigations
- Next Week: Nothing (annual leave)
- Time Spent (hrs): 1:15
- Replacement Bug-tracking Tool
- Planned:
- Actual:
- Next Week:
- Time Spent (hrs):