Services Unit Project Activity for WB 11/05/2015

  • Services Unit SL7 Desktop - 314 - Project314ServicesSL7
    • Planned: Neil - Nothing
    • Actual: Neil - Nothing
    • Next Week: Neil - Nothing
    • Time Spent (hrs): Neil - 0

  • Investigate AFS on ECDF storage - 268 - Project268AFSonECDF
    • Planned: New openafs component, testing of DA fileserver
    • Actual: New openafs component, no testing though.
    • Next Week: Testing and performance.
    • Time Spent (hrs): 7.1

  • Securing the Web - 287 - Project287SecuringWebServers
    • Planned: Possibly wind up
    • Actual: Nothing
    • Next Week: Possibly wind up
    • Time Spent (hrs): 0

  • Deploy Git/Gerrit as full services - 272
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Prometheus AFS Conduit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Research Data Audit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Archiving
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • CVS to SVN web
    • Planned: Hopefully resolve CoSign/Kerberos clash for SeaMonkey
    • Actual: Status check only
    • Next Week: Hopefully resolve CoSign/Kerberos clash for SeaMonkey
    • Time Spent (hrs): 0:30

  • Secure Web Server
    • Planned: Awaiting beta-test feedback
    • Actual: Status check only
    • Next Week: Awaiting beta-test feedback
    • Time Spent (hrs): 0:30

  • Replacement Bug-tracking Tool
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):
Topic revision: r2 - 15 May 2015 - 16:49:54 - NeilBrown
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback
This Wiki uses Cookies