Services Unit Project Activity for WB FILL_ME_IN

  • Services Unit SL7 Desktop - 314 - Project314ServicesSL7
    • Planned: Neil - Nothing
    • Actual: Neil - Nothing
    • Next Week: Neil - Nothing
    • Time Spent (hrs): Neil - 0

  • Investigate AFS on ECDF storage - 268 - Project268AFSonECDF
    • Planned: Demand attach server
    • Actual: Got basic demand attach server working. Going to need to update openafs component to do properly. Didn't spend as much time due to edweb move, and wordpress security update
    • Next Week: New openafs component, testing of DA fileserver.
    • Time Spent (hrs): 2.2

  • Securing the Web - 287 - Project287SecuringWebServers
    • Planned: Possibly wind up, but edweb hard deadline next week
    • Actual: Nothing. edweb and wordpress security issue
    • Next Week: Possibly wind up
    • Time Spent (hrs): 0

  • Deploy Git/Gerrit as full services - 272
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Prometheus AFS Conduit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Research Data Audit
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Archiving
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • CVS to SVN web
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Secure Web Server
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):

  • Replacement Bug-tracking Tool
    • Planned:
    • Actual:
    • Next Week:
    • Time Spent (hrs):
Topic revision: r1 - 01 May 2015 - 15:54:18 - NeilBrown
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback
This Wiki uses Cookies