SL7 Server progress to 19th of December 2016

The table and graph at the top of this page summarise the entire progress from the start of the SL7 server project to the 19th of December. The rest of this page concentrates on progress since the last report.

Dec stats

18 tickets resolved since last report.

Blockers?

Progress by unit

No unit is going to finish by the end of the year, but several think they'll finish the server upgrades early in 2017.

User Support

Since the last report User Support has upgraded salmon, trout, jekyll and hyde, with hubel and wiesel scheduled for this week.

https://wiki.inf.ed.ac.uk/DICE/Sl7USUnitUpgrade

Research and Teaching

https://wiki.inf.ed.ac.uk/DICE/ServerUpgradeSL7

Managed Platform

https://wiki.inf.ed.ac.uk/DICE/SL7MPUServersUpgrade

Infrastructure

http://www.dice.inf.ed.ac.uk/units/infrastructure/Projects/361-Inf-SL7-server-upgrade-umbrella/

Services

https://wiki.inf.ed.ac.uk/DICE/SL7ServicesServersUpgrade

-- RossArmstrong - 19 Dec 2016

Topic attachments
I Attachment Action Size Date Who Comment
pngpng sl7dec19th.png manage 48.1 K 19 Dec 2016 - 12:48 RossArmstrong  
Topic revision: r2 - 19 Dec 2016 - 12:57:57 - RossArmstrong
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback
This Wiki uses Cookies