2015 upgrade of the Forum server room edge switches

General setup plan

2920 switches

For each switch:

  • Pick a new switch from the pile.
  • Unbox and check over.
  • Enter the serial number and MAC address in the table below.
  • rfe lcfg/FSinstall2920, and set the MAC address.
  • Install the mounting lugs.
  • Install one 10GbaseT module in slot A (left) at the back of the switch.
  • Label the switch.
  • Rack up, and patch in port 48 to a suitable 'install' uplink.
  • Plug in, turn on, and watch while the self-test goes through.
  • Set up, as per the Setting up a ProCurve 2920 switch instructions. Note that there is a firmware upgrade required.
  • To download the active configuration to the switch, rfe core/install2920.pc and change the name of the portfile to that of the switch you are installing. Then ssh to abbado, and run make install2920.ets in /disk/home/abbado/Forum/core as root. Fix and repeat as necessary until this goes through cleanly.
  • Unrack, and place the switch on the Dexion racking, ready for installation.

Server room

Switch Serial no MAC In service
sr00 SG53FLYDSN 5C:B9:01:1D:99:40 DONE
sr01 SG53FLYDSJ 5C:B9:01:1D:05:80 DONE
sr02 SG53FLYDJL 5C:B9:01:1F:2E:40 DONE
sr03 SG53FLYDSW 5C:B9:01:1D:05:C0 DONE
sr04 SG53FLYDK8 5C:B9:01:1F:CE:C0 DONE
sr05 SG53FLYDKB 5C:B9:01:1F:2F:40 DONE
sr06 SG53FLYDSS 5C:B9:01:1D:29:C0 DONE
sr07 SG53FLYDSZ 5C:B9:01:1D:F8:80 DONE
sr08 SG53FLYDJJ 5C:B9:01:1F:4F:00 DONE
sr09 SG53FLYDRX 5C:B9:01:1D:19:00 DONE

Self-managed server room

Switch Serial no MAC In service
sr20 SG53FLYDKD 5C:B9:01:1F:FE:80 DONE
sr21 SG53FLYDSB 5C:B9:01:1D:55:C0 DONE
sr22 SG53FLYDSH 5C:B9:01:1D:F2:80 DONE
sr23 SG54FLYH8F 3C:A8:2A:4E:F1:80 DONE

2620 switches

For each switch:

  • Pick a new switch from the pile.
  • Unbox and check over.
  • Enter the serial number and MAC address in the table below.
  • rfe lcfg/FSinstall2620, and set the MAC address.
  • Install the mounting lugs.
  • Label the switch.
  • Rack up, and patch in port 49 to a suitable 'install' uplink.
  • Plug in, turn on, and watch while the self-test goes through.
  • Set up, as per the Setting up a ProCurve 2620 switch instructions. Note that there is a firmware upgrade required.
  • To download the active configuration to the switch, rfe core/install2620.pc and change the name of the portfile to that of the switch you are installing. Then ssh to abbado, and run make install2620.ets in /disk/home/abbado/Forum/core as root. Fix and repeat as necessary until this goes through cleanly.
  • Unrack, and place the switch on the Dexion racking, ready for installation.
Switch Serial no MAC In service
sr10 CN56DRV0Q1 34:64:A9:F4:59:40 DONE
sr99 CN56DRV0LP 34:64:A9:F4:39:40 DONE

-- JenniferOxley - 24 Jul 2015

Topic revision: r16 - 18 Jun 2017 - 10:15:03 - IanDurkacz
 