Final Project Report for Project 342 - Services Unit AT Decant

Scope of Project

This report covers work done by the Services Unit on project 342 - Services Unit AT decant work. There were two aspects to this work, the relocation of the printing facilities in Appleton Tower to suitable locations in Forresthill and the Wilkie Building and the relocation of two members of the Unit to new offices in the Wilkie Building. Of the two tasks, the former was the more tasking.

Implementation

As mentioned above, the majority of the effort spent as part of the project was expended in moving printing facilities to their new locations. For School owned kit, all that was required was to reach agreement with the various interested parties on the new locations of equipment and labelling them appropriately for the movers. Relocating the leased Xerox kit should have been even simpler since Xerox themselves did the actual moving but in fact a significant amount of effort was required to secure a suitable moving date from Xerox (we were very restricted in when the printers could move), supplying Xerox with all the information they required (things such as lift dimensions and doorway heights) and finally supervising the Xerox movers on the day of the move. There was also a small amount of work after the moves had taken place creating new print queues to reflect the new locations of the printer.

Effort spent

A total of 66.5 hours was spent on this project with less than a third of that being spent on office moves and the rest taken up by printer relocation.

-- CraigStrachan - 11 Sep 2015

Topic revision: r2 - 14 Sep 2015 - 08:59:45 - CraigStrachan
 