Approximately 1 month for fit-out which takes us up to 1st June
Fit out could include wiring new desks and installing new machines/monitors.
May get access before 30th April to start wiring closets.
AT
Start AT decant on 15th June - this date is still fluid
Exams are between 27th Apr and 22nd May.
Exam dates to be published on 2nd March.
BoE Meetings between 26th May and 9th June (level 4 open area, 4.14 and 4.03)
Cannot decant level 4 until after 9th June. Level 4 has approximately 60 flip-desks.
Phased decant starting at level 8. Plan is to decant 1 floor at a time on a weekly basis. (Can't see how this fits in to current schedule - we don't have 6 weeks.)
Commercialisation and COs moving to Wilkie.
Wilkie
Handover due on 15th May.
Allow a couple of weeks for fit out which takes us up to 1st June.
May get access before handover to start wiring closets etc.